Energy Transition at a Dead End

Energy Transition at a Dead End

The growing share of renewable energy, now combined with batteries, is creating new challenges that also require new solutions

Kaloyan Staykov for Capital, July 27, 2026

The political narrative surrounding the energy transition in the European Union often emphasizes its inevitability and boils down to a single, universal solution to every problem: more renewable energy sources. This highly simplified narrative overlooks one small detail—every technological (r)evolution generally depends on three key factors: the availability of technologies, the investment and operating costs of those technologies (including necessary subsidies), and administrative procedures. In other words, if you do not have physical access to the technology, if its installation and/or operation is too expensive, and if you encounter administrative barriers that make the entire process more costly or slow it down, there will be no energy transition.

Although there has been talk of an energy transition since the oil crises of the 1970s, the first real steps in this direction took more than two decades. The initial deployment of solar and wind power generation capacity was slow and arduous, due both to the limited production capacity of these technologies and their high cost. The EU’s solution to this problem was to set minimum targets for renewable energy sources (RES) in gross final electricity consumption and to provide subsidies for generation capacity. This led to a boom in new renewable energy capacity in member states between 2008 and 2012, which was followed almost everywhere by near-zero investment in the following decade.

Regardless, everyone is aware that this is more of a slowdown than an end to the energy transition, and the period is being used to proactively develop the electricity grids—both transmission and distribution. This, in turn, is enabling a second boom in the integration of renewable energy sources, which differs from the first. This time, the driving force is not government subsidies, but rather the low cost of borrowed capital and falling capital expenditures for generation capacity. Moreover, investor interest this time is much stronger in photovoltaic plants than in wind farms, a trend aided by a significant streamlining of administrative procedures. The scale of the new capacity is so large that the available grid connection capacity is rapidly being exhausted, and in many countries, waiting lists are forming for power plants seeking to connect to the grid.

After more than 20 years in which the focus of the energy transition has been on generation capacity—and with no clear end in sight to the current boom in renewable energy—Member States and the European Commission are beginning to pay more attention to the development of electricity grids. However, no matter how inexpensive a given technology is or how quickly it can be brought online, it is completely useless if its output cannot reach the end consumer. This is precisely the new major constraint on the pace of the transition: whether a given power plant can be connected to the grid, whether its generation can be scheduled without risking the stability of the system, and what this would mean for grid development.

The new phase of development in the electricity sector makes grid infrastructure a priority, yet the way it is planned, funded, and managed remains virtually unchanged. The logic behind the development of renewable energy sources (RES), which has prevailed over the past 20 years—whether rightly or wrongly—relies on overcapacity, concentration of assets, overproduction, and low or negative prices, as well as long-distance transmission. If all of this is applied to the expected development of the grids, planned as they have been so far, it would lead to excessively high costs, as we are seeing in many member states, although Bulgaria is not among them. Moreover, the focus is increasingly directed toward transmission grids, while distribution grids remain in the background.

This is extremely misguided and will lead to new problems for at least three reasons. The first is that the transmission and distribution networks operate as interconnected systems, and any problem in one is passed on to the other. In traditional power system planning, the distribution grid plays a relatively passive role—it receives the power flow and distributes it to end customers. In modern systems, however, it plays an active role, as it is connected to photovoltaic and wind power plants—52% of PV and wind power plants by 2025—as well as active consumers with their own renewable energy sources and storage systems, electric vehicles, and more. Let’s not forget that a few days after the nationwide power outage in Spain, the country’s transmission operator was unable to say what role the distribution networks played in the incident—whether they helped prevent it or made the situation worse.

The second point is that planning investments separately leads to suboptimal results. Although the roles, management, and investments in the two grids are very different—which is why they are regulated separately—their planning and development must be synchronized. This is intuitively clear to everyone and can easily be illustrated with the following anecdote: Imagine you’re planning a vacation with your significant other—you want to camp in the mountains, but your significant other wants to stay at a hotel by the sea. If you present them with a fait accompli and head to the mountains, it won’t be the end of the world, but don’t be surprised if you end up having an unpleasant vacation. Now imagine that, on top of that, you also have children who want high-speed internet, TV, bungee jumping, and so on—planning becomes more complicated.

The third point is that we have limited resources and cannot do everything we want right now. This leads to prioritizing, which sometimes limits the network’s expansion precisely where it’s most needed—when connecting new users. Even if we integrate all new renewable energy projects and storage systems, if there is insufficient demand to support them, we will find that we have invested too much for too little return. This is even more true if we look beyond the electricity sector to transportation and heating/cooling. The share of renewable energy in gross final electricity consumption will reach 47.5% in 2024, while this share is 26.6% for heating and cooling and only 11.2% for transportation. In other words, if we want both higher electrification and a higher share of RES in final consumption, this cannot happen without prioritizing and accelerating grid development.

The easy part of the energy transition is over. Those were the low-hanging fruits that could be picked without much effort. The growing share of renewable energy, now combined with electricity storage systems, creates new challenges that require new solutions. Grid capacity for connecting new generation capacity has been exhausted. In addition, transformation and transmission capacity is also running out, creating “congestion” in the grid and, consequently, constraints on generation capacity.

Last but not least, additional capacity is also needed to connect consumers. All of this costs money, takes time, requires the delivery of raw materials, supplies, machinery, and other resources, and involves workers. This is not about delaying the energy transition, but about better planning, which would allow it to proceed smoothly and without risk to the markets and the system. Otherwise, it will slow down on its own.