The German Federal Network Agency (Bundesnetzagentur) has announced the results of the first long-term capacity auction, which closed for bid submissions on 8 September 2026.
“The auction saw intense competition between different technologies – power plants and electricity storage facilities – resulting in relatively low bid prices. The results represent an important first step towards securing a long-term electricity supply at efficient cost. The geographical distribution of the successful bids will contribute to the reliable operation of the electricity grid,” said Klaus Müller, President of Bundesnetzagentur.
He emphasised that, as the electricity system becomes increasingly volatile, sufficient dispatchable capacity is needed to respond under all conditions. According to him, there is now certainty that this capacity will be built. Bundesnetzagentur will prepare the second auction without delay and take the necessary steps to launch the capacity market.
Auction results
The auction offered 4,500 MW of adjusted capacity (rMW), calculated by applying technology-specific derating factors that reflect the contribution of the respective capacity to security of electricity supply. A total of 41 bids were submitted, with a combined volume of approximately 11,958 rMW. Seven bids were disqualified, for example, due to missing legally required information or supporting documents.
Eleven bids were awarded, with a total capacity of approximately 5,160 rMW. This exceeded the initially announced auction volume of 4,500 rMW because the bid that crossed this threshold was awarded in full.
The largest volume of awarded capacity is located in North Rhine-Westphalia, with three projects totalling approximately 2,118 rMW. Brandenburg follows with four projects and 1,819 rMW, Saxony with two projects and 910 rMW, Bavaria with one project and 269 rMW, and Baden-Württemberg with one project and 45 rMW.
The volume-weighted average award price was €155,296 per rMW per year, significantly below the price cap of €244,000.
The successful bidders include:
RWE Generation SE – North Rhine-Westphalia;
Lausitz Energie Kraftwerke AG – Brandenburg and Saxony;
Gaskraftwerk Leipheim 20 GmbH – Bavaria;
Stadtwerke Karlsruhe GmbH – Baden-Württemberg.
Next steps
Detailed information on the results of the first long-term capacity auction has been published on the Bundesnetzagentur website.
Bundesnetzagentur is currently stepping up preparations for the second long-term capacity auction. The date of the auction will be announced on 10 November 2026, while the necessary preparatory work for launching the capacity market is also underway.
Source: Bundesnetzagentur